Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Please help!!!! Hannah can paint a room in 9 hours. Destiny can paint the same room in 15 hours. How long does it take for both Hannah and Destiny to paint the
a number that multiply by -15 can give me adding +2
1: 2.5A 90V R ? 2: 200 ohms 3.25mA V ? 3: 2.5kv 300 ohms I ?
Which is used to measure the length of a bicycle trail? A. km B. kg C. kmi D. kL
Which organization provides assistance to mothers and children living in poverty? WHO UNICEF World Bank Security Council
Three more than four times a number is 15
During spermatogenesis, which of the following undergoes meiosis II to produce four haploid mature sperm cells? Haploid primary spermatocyte Diploid secondary s
Metal Perestroika failed to improve the Soviet economy for all of the following reasons, EXCEPT __________. A. the lack of interest by foreign investors in open
What was the main idea behind the federalist papers? A: support of states" rights B: support of the bill of rights C: support of a strong federal government D:
a number increased by 10 is 114