15men can complete a piece of work in25days. how many men should be added to complete the same work in15days.​

Respuesta :

mhanifa
mhanifa mhanifa
  • 04-08-2021

Answer:

  • 10 men

Step-by-step explanation:

Amount of work done by 15 men is:

  • 15 men *25 day = 15*25 man*days

Same work can be done by 25 men, in 15 days, so 10 more men should be added.

Answer Link
abovejosh
abovejosh abovejosh
  • 04-08-2021
Answer: 10 men explanation: guy above me
Answer Link

Otras preguntas

During a thunderstorm​ yesterday, 600 millimeters of rain fell in 30 minutes. What is the unit rate for millimeters per​ minute? Use pencil and paper. Describe
Jen opens a bank account with a deposit of $100. over six years, the balance in the account changes at an increasing rate until it reaches a balance of $200
Problem 1. companies are advertising cigarettes right outside your school. you've heard your underage friends talk about smoking because of the advertisements.
Who holds the power in a unitary system of government?
6. Suppose that we are designing a completely randomized block design with 120 subjects, where the subjects are divided into two blocks of equal size. In this e
What to do in 49 days after death?
What is national debt
There are 5 Christmas trees in the town square. Four of the trees have 155 ornaments on them. The 5th tree is the largest and has 285 ornaments. How many orname
What is an example of fascism?
A person invested $210 in an account growing at a rate allowing the money to double every 10 years. how long, to the nearest tenth of a year would it take for t