men can do a work in 32 days in how many days will 24 men complete the same work​

Respuesta :

Аноним Аноним
  • 02-12-2020

Answer:

It will take 32/24, or 1 1/3 days, for 24 men to get the job done.

Step-by-step explanation:

Answer Link

Otras preguntas

Listen and select the option with the spelled word from the audio. A. Haya B. Jayo C. Hoyo D. Joya
Two buses 'A' and 'B' are moving in the same direction with the velocities 30m/s and 40m/s respectively. Find the relative velocity of the bus 'A' with respect
Which is equal to 4 hectometers? 0.04 kilometers 0.4 kilometers 0.004 kilometers
Find the unknown value (c).
I am a composite number that is between 10 and 20. I am even. I am square. What number am I?
A simile is a comparison made using _________, and a metaphor is a comparison made __________. Question 5 options: repetitive sounds/ without repetitive sounds
i need help with this real bad 0.75 (8 + e)=2-1.25e​
The social studies teacher wants to know whether the students in the entire school prefer a model United Nations activity or a student government activity. The
What is the meaning of "implicit"? Found in a text Stated from evidence Stated directly Implied by the text
Pam bought a toaster oven for $99 with a 15% off O coupon. A week later she finds out the same oven is on sale for $89 at a nearby store. Did she get a better